Real Betis indeed recognize that Benito Villamarín’s new job will last for more than two seasonsso I assume so Third campaign It will be outside Heliopolis at Cartoga Stadium. Özgür Unayadvisor … For the club responsible for infrastructure, and Federico Martinez GalleryGeneral Manager, appeared in Betis TV To report on how the preferred work is progressing and the subsequent complete redesign of the outdoor area and park, following two recent Sundays, where progress has been made. SpanishThe entity opened a direct negotiation process with many contracting companies, as the proposals presented in the tender for awarding these offers were not accepted.
FC Betic assumes that everything will last longer than initially planned for the two seasons: “Initially our strategic plan and our business plan I planned to implement the project in two seasons. The idea finally sticks, but it’s true that given the situation and our deadlines, It will likely be more than two seasons. This has already been planned, This possibility has already been included in the contract with CartujaBecause it was there from the beginning Some aspects and doubts that were not explicitly based on Betis We had, for prudent reasons, to take into account this possibility that it seems that we will have to confirm as soon as we receive the final offer from the construction company, since one of its results will be a schedule that matches our needs and intentions,” admitted Martínez Feria.
Ozgur Unay explained about the process, “The flashy part of the demolition process is over, which is the demolition of a 45-meter-high platform, but this is not over yet. There are still thousands of tons of rubble removed, and now the important work begins, because we now have to recycle everything and use it for environmental reasons,” while Martinez Feria added that “Until the end of the year, we will continue the demolition phase of the preference platform, and in the first quarter of 2026 we will begin the excavation phase. The work does not stop and continues at its own pace.”
The consultant responsible for the infrastructure continued: “From this moment we open a collaborative process, which is very common in this type of work, at the same time we finish the demolition, so the work has never stopped and will not stop, because in the end it connects one thing to the other: the expectations in terms of schedule and planning are that this process will lead to a successful bidder in the first quarter of 2026, and immediately after the completion of the demolition let us begin.” With the containment screen and at the same time let us also continue to improve the project. We are working on the demolition schedule and the next step is to start with a containment screen around the perimeter of the parking lot. And the basements of the stands. Now we’re going to open a New bidding processr both the containment screen and the rest of the project, which will be a Collaborative projectOur goal is for the same company to implement it,” Ozgur Unay concluded.